CRM implementation officially launched on Thursday, June 5th! This marks an exciting milestone as we begin transforming how we connect, collaborate, and engage. There’s a lot ahead, and we’re thrilled to have you on this journey. Click here to access the slide deck from our kickoff event!
Sprints officially kicked off the week of June 16th! With cross-functional teams diving into focused work, we’re now translating vision into action, one sprint at a time. Each iteration is packed with collaboration, innovation, and real progress toward bringing our CRM to life.
What is a sprint?
A “sprint” refers to work done within a specific time frame. Our sprints will typically run for 6 weeks with 2 weeks of planning, 2 weeks of building, and 2 weeks of testing. Each sprint will be topic-based (Epic) and addressed by a cross functional team that concentrates on a defined set of tasks or user stories.
The first “sprint”, led by Attain Partners and focused on Bio/Demo, began the week of June 16 and will continue through the end of the calendar year.
You can find more details about our Sprints linked click here.
What is an Epic?
A large body of work, such as a major feature or capacity, that can be broken down into smaller tasks, work items and user stories that will be worked on across multiple sprints.
How do sprints work in this implementation?
- Sprint Duration – Typical length of sprints 6 weeks with 2-week cycles.
- Sprint Planning – How the team prioritizes user stories and tasks for each sprint.
- Sprint Execution – Participants work together to configure, test, and validate Salesforce features.
- Sprint Review – Stakeholders provide feedback on completed work.
- Epic Retrospective – Lessons learned and process improvements for future sprints.